Capital Improvement Projects

The following list is a summary of active Capital Improvement Projects within the city limits of Hoover.  As individual projects progress, this list will be updated. 


ALL PROJECTS AS OF SEPTEMBER 2018

ALL PROJECTS AS OF SEPTEMBER 2018
Project Type Lead Agency Status Current Status (% Complete) Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141.
Jefferson County Utility Relocation 5% Construction 03/28/19
Eden Ridge at S. Shades Crest Rd - Adds left turn lane to South Shades Crest Rd and realigns Shades Run Circle. City of Hoover Construction 75% Completion 12/15/18
Galleria Blvd Extension - County lead project that extends Galleria Blvd. by Chick-Fil-A to Old Montgomery Hwy.  For additional information on this project, contact Jefferson County Roads​ and Transportation at (205) 325-5141. Jefferson County ROW Acquisition 30% Utility Relocation 02/01/19
Alford Ave @ Shadybrook - Realigns Shadybrook Ln and widens Alford Avenue with a left turn lane. City of Hoover Construction 80% Completion 10/15/18
Hwy 150 @ Ross Bridge Pkwy - State lead project that widens Hwy 150 to five lanes from Shades Crest Rd to Lake Cyrus Blvd.  For additional information on this project, contact ALDOT's Birmingham Area Office at (205) 328-5820. ALDOT Construction 85% Completion 10/15/18
Valleydale Rd Widening (Little) - Widens Valleydale Rd to five lanes from Hwy 31 to Riverchase Parkway. City of Hoover Design 95% ROW Acquisition 10/15/18
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. City of Hoover ROW Acquisition 85% Utility Relocation 03/01/19
Stadium Trace Pkwy at Brocks Gap Pkwy - Adds new turn lanes and extends existing turn lanes for each of the four intersection approaches. City of Hoover Construction 2% Completion 06/01/19
S. Shades Crest Rd additional northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes drive to Hwy 150. City of Hoover Design 30% ROW Acquisition 09/01/18

SIDEWALKS, GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave. City of Hoover ROW Acquisition 50% Utility Relocation 06/01/19
Cahaba/Riverchase Greenway - Constructs parking, trail head and new trail on city-owned property adjacent to Riverchase Elementary school and the Cahaba River. City of Hoover Design 100% Construction 12/01/18
Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. City of Hoover Design 0% ROW Acquisition 02/01/19
Bluff Park Sidewalks - Constructs sidewalks on multiple streets in Bluff Park. City of Hoover ROW Acquisition 85% Utility Relocation 01/31/19
Alford Avenue Sidewalks, Phase 1 - Constructs sidewalk along Alford Avenue from Haden Street to Pine Lane and along Haden St from Alford Ave to Blue Ridge Blvd. City of Hoover Design 0% ROW Acquisition 03/01/19
Bike/Pedestrian Master Plan Update - Update of the 1999 Bicycle/Pedestrian Master Plan. City of Hoover Finalizing 95% Adoption 11/19/18
Inverness Community Greenway - Constructs sidewalk and trail along Inverness Parkway from Valleydale Rd, through the City's Inverness Nature Park. City of Hoover ROW Acquisition 99% Construction 01/01/19

PARKS & FACILITIES

         
Bluff Park Pavilion - Replaces aging community center with a pavilion. City of Hoover Design 95% Construction 11/01/18
Police Training Facility - Constructs new police training facility on Municipal Drive next to Fire Station 4. City of Hoover Design 95% Construction 11/01/18
City Hall 3rd Floor Renovations - Renovate 3rd floor city hall administrative offices and Council Chambers. City of Hoover Design 35% Construction 11/01/18
Star Lake Improvement - Upgrades Star Lake Park by creating one-way traffic around the lake, widening and replacing the existing sidewalk and improving parking. City of Hoover Design 20% Construction 03/01/19

GENERAL / MISC

.
         
US Highway 31 Street Light Replacement, Phase 1 - Installs new street lighting along Hwy 31 from the Cahaba River Bridge to Patton Chapel Rd. City of Hoover Construction 87% Completion 10/12/18